Deprecated: Unparenthesized `a ? b : c ? d : e` is deprecated. Use either `(a ? b : c) ? d : e` or `a ? b : (c ? d : e)` in /var/www/vhosts/sthilliers.com.au/staging.sthilliers.com.au/wp-content/plugins/flow-flow/includes/LABase.php on line 260
Enhanced Land Force Stage 2C - Greenbank Training Area, QLD | St Hilliers

Enhanced Land Force Stage 2C – Greenbank Training Area, QLD

Client

Department of Defence

Location

Greenbank, QLD

Value

$110m

Contract type

HC-1 2003 - Construct Only

Completion

Sep 14

The Greenbank Training Area Project involved the construction of additional training facilities, accommodation and supporting infrastructure, across a 4,600 hectare site, to support an increase in Defence training activities. As the Head Contractor for the works, St Hilliers successfully delivered the challenging 7 stage Project, having met all Defence requirements and handing over the site within the required 16 month program.
The project required the installation of:

  • 61 Buildings with 10km of new roads (rated to support loads between 40t and 70t);
  • 339,000m3 of cut to fill;
  • 160,000m2 of asphalt and road pavements, consisting of 7 pavement types, varying between 600 and 1,300mm deep;
  • 170,000m3 of road pavement construction material;
  • 7,000m3 of concrete;
  • 130t reinforcement;
  • 3 bridges;
  • 8km of high voltage cabling, communication, potable and non-potable water installed in ground, all needed to be coordinated with the road construction program;
  • 800,000 litres of underground rain water storage;
  • New sewer treatment plan; and
  • 10km of fencing.

Recent Projects

View more
/$10.8m
Fire School Simulator and Water Recycling Works, Amberley QLD
View Project
/$5.7m
Fleet Base East – Garden Island Building Works, NSW – Project 2
View Project
/$4.1m
RAAF Base Pearce Potable Water Infrastructure Project, WA
View Project